Oil Platform Hook-up, Commissioning Contract for Kvaerner

January 2, 2013

ConocoPhillips confirms options in the Eldfisk 2/7 S topside contract for Kvaerner to perform offshore hook-up & commissioning assistance.

In March 2011, Kvaerner was awarded a contract by ConocoPhillips to perform engineering, procurement and construction (EPC) of the topside for the Eldfisk 2/7 S platform in the North Sea, with an estimated contract value of NOK 5.5 billion. ConocoPhillips has now confirmed options in the contract to perform offshore hook-up and commissioning assistance, which will add approximately NOK 400 million to the contract value.

The topside consists of one combined living quarter and utility module and a combined process and wellhead module, with a total weight of 15,500 tons. In addition, the contract includes the fabrication of two bridges, one bridge support module and a flare.

The offshore activities are planned to take place in 2013 for hook-up of the bridges and in the second half of 2014 for the topside modules.
The Eldfisk field is located in the Greater Ekofisk Area and has been in production since 1979. 
Contract partner for the work is Kvaerner's subsidiary, Kvaerner Stord AS.


Logistics News

DP World Begins $165 Million Expansion of Maputo Container Terminal Capacity

DP World Begins $165 Million Expansion of Maputo Container Terminal Capacity

Port Canaveral Invests $500 Million in Five-Year Port-Wide Improvement Plan

Port Canaveral Invests $500 Million in Five-Year Port-Wide Improvement Plan

Syria Signs New 30-Year Deal with CMA CGM

Syria Signs New 30-Year Deal with CMA CGM

Adani Ports Sees Higher FY26 Revenue Growth on Robust Volumes

Adani Ports Sees Higher FY26 Revenue Growth on Robust Volumes

Subscribe for Maritime Logistics Professional E‑News

South Korea's FLC purchases about 60,000 metric tonnes of feed wheat, traders claim
CANADA-CRUDE-Discount on Western Canada Select heavy crude narrows; remains historically tight
Tunisia receives offers for 25,000 T of restricted barley, traders report