Panama to Assess if Seepage Will Delay Expanded Canal Opening

September 9, 2015

 

During the testing phase of the new Pacific locks for the Panama Canal, some water seepage was detected in a specific area of the new Pacific Locks in a section that separates the middle chamber and lower chamber, as they were being stressed tested through exposure to level differentials much higher than those required for normal operations, but that may occur during dry-chamber maintenance works in the future.

The ACP is now awaiting a formal report from GUPC following detailed inspections. The report, will be inclusive of the root cause analysis conducted, as well as the recommended repair methodology. Upon evaluating the report's findings, the ACP will assess and communicate if the project's completion timeline will be altered in any way.

At this time, ACP has designated two independent external structural engineers to conduct an objective evaluation of the reasons for this localized issue and assess GUPC's solution.

While this important step takes place, the ACP is encouraged by the overall progress of the program, which has now reached 93 percent completion. Parallel work presses ahead with testing in other areas; the removal of the strip of land - known as a ‘plug'- separating the new Cocolí Locks from the Pacific Ocean, and the culmination of the Pacific Access Channel work. Likewise last week the removal of the dike or plug that separates the Atlantic ocean waters from the new Atlantic Lock was initiated and progresses at a good pace.

GUPC has the obligation to ensure the long-term performance on all aspects of the construction of the locks and to correct this deficiency. Moreover, GUPC's contract with the ACP dictates that the group is responsible for modifications and corrections that may be required. As with all of its operations and its infrastructure improvement projects, the ACP is committed to deliver world-class services and products.

As it has been the case for more than 100 years, the ACP maintains its commitment to safe, reliable and efficient service. Updates will continue to be issued as information becomes available to ensure that customers, the Panamanian people and all other key stakeholders are informed on the latest developments of the program.

Logistics News

CMA CGM Acquires Fattal Group

CMA CGM Acquires Fattal Group

Democratic Republic of Congo Copper Exports Fall 15%, Cobalt Rebounds

Democratic Republic of Congo Copper Exports Fall 15%, Cobalt Rebounds

New Pedestrian and Cycle Bridge Transported to Stockholm by Sea

New Pedestrian and Cycle Bridge Transported to Stockholm by Sea

BIMCO: Global Seaborne Crude Shipments Drop 16% Since Start of the Iran War

BIMCO: Global Seaborne Crude Shipments Drop 16% Since Start of the Iran War

Subscribe for Maritime Logistics Professional E‑News

As the Middle East conflict shakes markets, global companies are delaying IPOs and cutting dividends.
The US power and natgas price turn negative in Texas, California and other states due to mild weather
US truckers' diesel spending on Middle East conflict reaches record high