Cheniere to Roll Out Second LNG Unit

May 26, 2016

 Cheniere Energy Inc. plans to start exporting liquefied natural gas in August from a second plant at its Sabine Pass terminal in Cameron Parish, according to a report from Bloomberg News. 

 
Cheniere began exporting LNG in February from its first unit at Sabine Pass. In its fourth-quarter report, Cheniere said the second unit could begin producing LNG by mid-2016. 
 
When completed, the Sabine Pass facility will have six LNG units. The first two units have a combined production capacity of 9.9 million tons LNG per year.
 
“Actual project progress supports the achievement of substantial completion for Trains 1 and 2 by late May 2016 and September 2016, respectively," the company said in the filing with the Federal Energy Regulatory Commission.
 

Logistics News

Tanco Boosts Jeffersonville Port Capacity with $750K Fertilizer Expansion

Tanco Boosts Jeffersonville Port Capacity with $750K Fertilizer Expansion

BIO-UV Completes First Containerized Ballast Water Treatment Deployment

BIO-UV Completes First Containerized Ballast Water Treatment Deployment

Capesize Values Hit 17-Year High

Capesize Values Hit 17-Year High

Maritime and Coastguard Agency Advances Marine Safety with Multiverse Data Upskilling

Maritime and Coastguard Agency Advances Marine Safety with Multiverse Data Upskilling

Subscribe for Maritime Logistics Professional E‑News

US to expect more flight delays, as controllers will soon miss their paychecks
Maguire: Malaysia's coal blitz shows how other nations are able to capitalize on the LNG boom.
Carney: Canada is ready to resume trade talks with the US