Register now for the Port of the Future Conference • 2 Days, 50 Ports • Houston/Galveston area, TX • April 12–14, 2027

Army Corps Making Plans for Fort Langley-Eustis Construction

March 23, 2022

(Image: USACE)
(Image: USACE)

The U.S. Army Corps’ Norfolk District seeks contractors for the 3rd Port Improvements Project at Ft. Eustis, Va. Total award could be between $10 million and $25 million. The Corps will use responses from companies to “determine an acquisition strategy.” Go to SAM.gov and use ID W9123622B2017 to search. Responses are due March 28.

As envisioned now, this would be a firm-fixed-price contract for the construction of improvements at 3rd Port, JBLE–Eustis (Joint Base Langley-Eustis, in Newport News). The overall project includes a number of sub-projects:

  • Construction of three new finger piers to replace three existing piers that will be demolished and removed;
  • New bulkheads along piers 8 thru 14;
  • New utility connections at the three new pier locations to accommodate shore power, domestic water, sanitary wastewater, and bilge wastewater for six boats;
  • Removal of an existing mooring pile line on the north side of the Skiffes Creek Channel (approximately 800 ft long), and the installation of a new re-aligned mooring pile line on the channel’s north side;
  • Demolition of existing concrete pavement and placement of new pavement adjacent to the new piers; and,
  • Minor dredging – approximately 20,000 CY – in the area of the new pier location, as well as the new re-aligned mooring pile line.

Supporting work includes site development, utilities and connections, lighting, paving, and site improvements.  All utility work required by the contract documents will need to be coordinated with the privatized utility providers at JBLE-Eustis.

Send questions and correspondence to Allen Brainerd at [email protected] and a copy to Dianne Grimes at [email protected].

Logistics News

China Ships First Large Cargo of Brazilian Sorghum

China Ships First Large Cargo of Brazilian Sorghum

Conoship Adds 40-MWh Battery-Electric Option to CIP3800 Coaster

Conoship Adds 40-MWh Battery-Electric Option to CIP3800 Coaster

MoU Signed to Verify Emissions Reduction Through AI-Based Voyage Optimization

MoU Signed to Verify Emissions Reduction Through AI-Based Voyage Optimization

Sallaum Lines Launches European Automotive Logistics Company

Sallaum Lines Launches European Automotive Logistics Company

Subscribe for Maritime Logistics Professional E‑News

South Korean container ship to test Arctic route from Europe amid Western concerns
Shein postpones IPO until September 1, according to sources
Shein delays Hong Kong debut until September, SCMP reports