New Suez Canal Almost 84 Pct Complete

June 13, 2015

 Over 216 million cubic meters of water-saturated sand have been removed so far as part of the Suez Canal Development Project, said Head of the Suez Canal Authority Mohab Mamish.

 
This represents about 84 percent of the total cubic meters that should be dredged as part of the project, Mamish added.
 
Thirty-eight dredgers are working in the project, said Wagdi Zaki, the executive director supervising the dredging process, in statements on Thursday 11/06/2015.
 
The expansion project will pave the way for a transit of ships of up to 20 meters in draft, thus increasing the revenue of the canal to up to USD 17 billion a year.
 
The project aims at expanding the Suez Canal region's role as a global, industrial, and logistics center that is environmentally balanced with an integrated economy.
 
It is also projected to become a global hub due to its logistics and industrial services.
 

Logistics News

Maersk’s 2025 Report: Some Records and Some Lay Offs

Maersk’s 2025 Report: Some Records and Some Lay Offs

Panama President: Future Port Contracts Will Not Be Issued to a Single Operator

Panama President: Future Port Contracts Will Not Be Issued to a Single Operator

Cuba-Related Tanker Loads Gas Cargo in Venezuela

Cuba-Related Tanker Loads Gas Cargo in Venezuela

2027 Set as Operational Start of Petronor E-Fuels Plant at Port of Bilbao

2027 Set as Operational Start of Petronor E-Fuels Plant at Port of Bilbao

Subscribe for Maritime Logistics Professional E‑News

DSV aims to lower freight rates but faces port pressures with the return of Red Sea routes
Emirates could order Airbus A350-2000 wide-body jets
Spirit Airlines wants to transfer two Chicago airport gate to United Airlines for $30 Million