New Suez Canal Almost 84 Pct Complete

June 13, 2015

 Over 216 million cubic meters of water-saturated sand have been removed so far as part of the Suez Canal Development Project, said Head of the Suez Canal Authority Mohab Mamish.

 
This represents about 84 percent of the total cubic meters that should be dredged as part of the project, Mamish added.
 
Thirty-eight dredgers are working in the project, said Wagdi Zaki, the executive director supervising the dredging process, in statements on Thursday 11/06/2015.
 
The expansion project will pave the way for a transit of ships of up to 20 meters in draft, thus increasing the revenue of the canal to up to USD 17 billion a year.
 
The project aims at expanding the Suez Canal region's role as a global, industrial, and logistics center that is environmentally balanced with an integrated economy.
 
It is also projected to become a global hub due to its logistics and industrial services.
 

Logistics News

DNV Publishes Recommended Practice for Onboard Carbon Capture, Storage

DNV Publishes Recommended Practice for Onboard Carbon Capture, Storage

Don Davis Appointed as New Managing Director at OCIMF

Don Davis Appointed as New Managing Director at OCIMF

Misaligned Charter Terms Amounts to $110,000 Shipbroker Settlement

Misaligned Charter Terms Amounts to $110,000 Shipbroker Settlement

ABS Fortifies Digital, Remote Support for Offshore Energy

ABS Fortifies Digital, Remote Support for Offshore Energy

Subscribe for Maritime Logistics Professional E‑News

Former Spanish transport minister sentenced to 24-years for corruption
Heatwave to spread across the UK, breaking June records
Experts say China's efforts to use green energy in AI projects face hurdles.