New Suez Canal Almost 84 Pct Complete

June 13, 2015

 Over 216 million cubic meters of water-saturated sand have been removed so far as part of the Suez Canal Development Project, said Head of the Suez Canal Authority Mohab Mamish.

 
This represents about 84 percent of the total cubic meters that should be dredged as part of the project, Mamish added.
 
Thirty-eight dredgers are working in the project, said Wagdi Zaki, the executive director supervising the dredging process, in statements on Thursday 11/06/2015.
 
The expansion project will pave the way for a transit of ships of up to 20 meters in draft, thus increasing the revenue of the canal to up to USD 17 billion a year.
 
The project aims at expanding the Suez Canal region's role as a global, industrial, and logistics center that is environmentally balanced with an integrated economy.
 
It is also projected to become a global hub due to its logistics and industrial services.
 

Logistics News

Oil Loading in Venezuela Crawls After New US Interceptions

Oil Loading in Venezuela Crawls After New US Interceptions

FMC Investigates Spain’s Restrictive Port Practices

FMC Investigates Spain’s Restrictive Port Practices

Baku Port Handles 37% More Containers in 2025

Baku Port Handles 37% More Containers in 2025

International Flag-State Association Looks to Advancing Role in Policymaking

International Flag-State Association Looks to Advancing Role in Policymaking

Subscribe for Maritime Logistics Professional E‑News

Officials say that the US is pursuing a third oil tanker near Venezuela
Source: Russia's pipeline exports of gas to China have increased by 25% in the past year.
Air India 777 aircraft returns after engine oil pressure drops, regulators say