Panama Canal Expansion 96% Complete

December 21, 2015

(ACP file photo showing construction underway at the Panama Canal)
(ACP file photo showing construction underway at the Panama Canal)
The Panama Canal Authority (ACP) announced that the first-ever expansion is 96 percent complete.
 
A video of recent progress can be seen here.
 
In line with this, ACP CEO/Administrator Jorge L. Quijano provided a next-step update at an industry event Friday in Panama City. 
 
The key points:
  • Locks reinforcements are scheduled to be completed mid-January 2016.
  • Testing of locks reinforcements and additional testing will occur next.
  • In April, transit trial tests with a chartered vessel in the Atlantic locks will occur (following conversations with GUPC).
  • A date for the expansion’s inauguration will be then be selected, expected to be in the second quarter of 2016. Subsequently, the commercial opening date will be selected. The opening will be soon after the inauguration.
  • The ACP is building the expanded Canal for the long haul, and quality and testing are critical. The ACP will continue to provide updates on the project as more progress and information is made available.

Logistics News

Baltic Index Rises, Sees Gains Across All Vessel Sizes

Baltic Index Rises, Sees Gains Across All Vessel Sizes

Cuba Maritime & Port Celebrates Three Years of Industry Innovation and Collaboration

Cuba Maritime & Port Celebrates Three Years of Industry Innovation and Collaboration

Melvin Resigns as President of South Carolina Ports Authority

Melvin Resigns as President of South Carolina Ports Authority

Brazil Ships More Iron Ore to China, Competitors Lag

Brazil Ships More Iron Ore to China, Competitors Lag

Subscribe for Maritime Logistics Professional E‑News

Drone attacks on Russian energy sites
Tour bus rolls over on New York highway, causing multiple deaths
Drop in wind power production to boost Monday spot prices