Panama Canal Expansion 96% Complete

December 21, 2015

(ACP file photo showing construction underway at the Panama Canal)
(ACP file photo showing construction underway at the Panama Canal)
The Panama Canal Authority (ACP) announced that the first-ever expansion is 96 percent complete.
 
A video of recent progress can be seen here.
 
In line with this, ACP CEO/Administrator Jorge L. Quijano provided a next-step update at an industry event Friday in Panama City. 
 
The key points:
  • Locks reinforcements are scheduled to be completed mid-January 2016.
  • Testing of locks reinforcements and additional testing will occur next.
  • In April, transit trial tests with a chartered vessel in the Atlantic locks will occur (following conversations with GUPC).
  • A date for the expansion’s inauguration will be then be selected, expected to be in the second quarter of 2016. Subsequently, the commercial opening date will be selected. The opening will be soon after the inauguration.
  • The ACP is building the expanded Canal for the long haul, and quality and testing are critical. The ACP will continue to provide updates on the project as more progress and information is made available.

Logistics News

Ship Design, Maritime Accidents and There’s a Master on the Run

Ship Design, Maritime Accidents and There’s a Master on the Run

Maersk: Effective US Tariffs Average Around 21% Currently

Maersk: Effective US Tariffs Average Around 21% Currently

US Grain Shipments Surge 9% in face of Chinese Tariffs

US Grain Shipments Surge 9% in face of Chinese Tariffs

Great Lakes Limestone Trade Up in June

Great Lakes Limestone Trade Up in June

Subscribe for Maritime Logistics Professional E‑News

Liverpool players carry red wreaths to Diego Jota funeral
Japan braces for more quakes, authorities dismiss doomsday hype
French President Macron announces 'historic' Airbus/Malaysia Airlines deal