Melkøya Start-Up Postponed

November 23, 2009

The Snøhvit facilities at Melkøya have been shut down this autumn for planned upgrading and maintenance. Running-in after the completion of the turnaround began on 7 November.

All replaced and upgraded parts of the cooling plant were started up and appeared to function. But two technical challenges have arisen during this phase. The first was a fault in one of the plant’s utility systems, which has now been repaired. Arising later in the running-in period, the second fault related to an electric motor which forms part of the cooling process.

It has now been decided that this motor must be replaced by a reserve unit which is stored at the nearby Polarbase in Hammerfest. Replacement work is already well under way, and personnel from the operations organisation and the contractor will work around the clock until the plant is ready to resume start-up. The unexpected faults which have occurred during the first running-in phase are not related to the work done during the turnaround.
 

Logistics News

CMA CGM Q1 Resilient, but Shipping Margins Tighten Amid Geopolitical Turbulence

CMA CGM Q1 Resilient, but Shipping Margins Tighten Amid Geopolitical Turbulence

EU Temporarily Suspends Fertilizer Duties Amidst Hormuz Crisis

EU Temporarily Suspends Fertilizer Duties Amidst Hormuz Crisis

Syria, CMA CGM to Operate Two Dry Ports

Syria, CMA CGM to Operate Two Dry Ports

Jon Oakey, Retired Port of Aberdeen CFO, Wins Finance Lifetime Achievement Award

Jon Oakey, Retired Port of Aberdeen CFO, Wins Finance Lifetime Achievement Award

Subscribe for Maritime Logistics Professional E‑News

Sources say that the Brazil Development Bank BNDES has sold its stakes in Axia Energia and Petrobras.
Swiss sanctions against Russia and Belarus are in line with EU actions
CMA CGM profits drop as Iran War weighs on shipping