Melkøya Start-Up Postponed

November 23, 2009

The Snøhvit facilities at Melkøya have been shut down this autumn for planned upgrading and maintenance. Running-in after the completion of the turnaround began on 7 November.

All replaced and upgraded parts of the cooling plant were started up and appeared to function. But two technical challenges have arisen during this phase. The first was a fault in one of the plant’s utility systems, which has now been repaired. Arising later in the running-in period, the second fault related to an electric motor which forms part of the cooling process.

It has now been decided that this motor must be replaced by a reserve unit which is stored at the nearby Polarbase in Hammerfest. Replacement work is already well under way, and personnel from the operations organisation and the contractor will work around the clock until the plant is ready to resume start-up. The unexpected faults which have occurred during the first running-in phase are not related to the work done during the turnaround.
 

Logistics News

Puerto Rico Inks LNG Contract with New Fortress Energy

Puerto Rico Inks LNG Contract with New Fortress Energy

Panama Canal Unveils Decade Roadmap of Transformation

Panama Canal Unveils Decade Roadmap of Transformation

Nissen Kaiun Becomes Stakeholder in Econowind

Nissen Kaiun Becomes Stakeholder in Econowind

China's Hold on Global Ports focus of Trump Administration

China's Hold on Global Ports focus of Trump Administration

Subscribe for Maritime Logistics Professional E‑News

Maguire: UK gas traders must be aware of the weather this winter.
The U.S. restores Hungary to full status under the visa waiver program
Allegro, an e-commerce company, teams up with DPD to launch a delivery program