Sevan, Cosco Agree Rig Delivery Delay

October 16, 2015

 Norway-headquartered drilling contractor Sevan Drilling and Chinese shipbuilder Cosco Corporation have agreed to delay the end of the first deferral period for cylindrical ultra deep water drilling rig Sevan Developer from 15 October 2015 to 1 November 2015.

 
In May 2011, Sevan Drilling entered into a contract with Cosco for the construction of Sevan Developer, based on the same design as other Sevan Drilling rigs.
 
Sevan Drilling announced that the agreement is for both parties to “continue negotiations of the first six-month option period.”
 
Under the contract, COSCO was to deliver the rig in October 2014. However, construction was delayed because of lack of equipment from subcontractors.
 
At that time, delivery was put back by a year, with options exercisable at a six-month interval to further extend the delivery date up to a total of 36 months, until October 2017.
 
Because of the delay, COSCO runs the risk of being liable to pay compensation. In the meantime, Sevan Drilling is unable to fix a charter contract for the rig.
 

Logistics News

TOTE Promotes Hofeling, Crawford

TOTE Promotes Hofeling, Crawford

Russian Yamal LNG Plant Ships First Cargo This Season Via Northern Sea Route

Russian Yamal LNG Plant Ships First Cargo This Season Via Northern Sea Route

Maersk Pauses Haifa Port Calls

Maersk Pauses Haifa Port Calls

First BYD Electric Cars Delivered to Mexican Port

First BYD Electric Cars Delivered to Mexican Port

Subscribe for Maritime Logistics Professional E‑News

Air India is warned by India's watchdog for violating the pilots' duty hours
China's teapots are slowing the purchase of Iranian oil, resulting in steeper discounts on Iranian oil
After Israel's attack on Iran, airlines suspend flights