Sabine Pass LNG Plant Suffers Outage

January 22, 2018

File photo: Cheniere Energy
File photo: Cheniere Energy
Production at Cheniere Energy's Sabine Pass liquefied natural gas (LNG) export plant in Louisiana is running well below capacity, resulting in disruption to cargo loadings, trade sources said.

Feed gas supply into the liquefaction plant plunged sharply during the weekend, data on the Thomson Reuters Eikon terminal showed.

Flows fell to 630 million cubic feet/day on Jan. 19 from 3.2 billion cubic feet/day on Jan. 15.

Freezing weather may have disrupted water supply to Sabine Pass, market sources said.

Several production units, or trains, are estimated to be offline, potentially delaying cargo loadings and deliveries to Asian markets in February and March, they said.

Cheniere Energy was not immediately available to comment.


Reporting by Oleg Vukmanovic and Jessica Jaganathan

Logistics News

USACE Introduces System for Assessing Pre-Construction Notifications

USACE Introduces System for Assessing Pre-Construction Notifications

Project Freedom Gets Off to a Troubled Start

Project Freedom Gets Off to a Troubled Start

Former MARAD Deputy Administrator Sang Yi Appointed AAPA President, CEO

Former MARAD Deputy Administrator Sang Yi Appointed AAPA President, CEO

Fratelli Cosulich Launches Newest Methanol Vessel

Fratelli Cosulich Launches Newest Methanol Vessel

Subscribe for Maritime Logistics Professional E‑News

Wesfarmers, Australia's largest retailer, increases retail prices to offset rising freight costs
Drones disrupt relative calm for months in Sudan's capital and hit airport
Kazakh airline Air Astana's loss triples as costs rise