CIS Installs Conductors in Southern North Sea

January 12, 2016

Conductor Installation Services Ltd (CIS), an Acteon company that provides hammer services to install conductors and drive piles, announced that it has completed its second conductor installation operation during the last 12 months for a North Sea oil and gas operator.

Work was carried out on a gas development project in the Southern North Sea. CIS installed six 30-inch conductors on the project to form the foundations of six development wells. In addition, CIS supplied all conductor-running services, handling equipment, together with drive shoes that improve driveability by 40 percent.

Following completion of a comprehensive drive study, CIS crew worked with rig contractor Ensco and the operator to commence the driving operation. CIS worked from the jack-up rig Ensco 80, and used a 90 kJ hydraulic hammer to drive all six conductors to their target depth on the wellhead platform. Conductors were driven as deep as 401 feet from the rig floor to the conductor toe, reaching a depth of 158 feet below the mudline.

Earlier this year, CIS carried out a pile-driving campaign on the same development that was completed 17 hours ahead of schedule.

Logistics News

How JobMarineMan Is Building a Direct Crew Recruitment Ecosystem

How JobMarineMan Is Building a Direct Crew Recruitment Ecosystem

Baltic Index Reaches One-Week High on Higher Capesize Rates

Baltic Index Reaches One-Week High on Higher Capesize Rates

NYK Group’s ICO Launches Belgium’s First Shore Power Facility for RoRo Ships

NYK Group’s ICO Launches Belgium’s First Shore Power Facility for RoRo Ships

BMT, Austal Sign Engineering Alliance to Support Shipbuilding Projects

BMT, Austal Sign Engineering Alliance to Support Shipbuilding Projects

Subscribe for Maritime Logistics Professional E‑News

Multiple injuries reported after two trains collided north of London
Trump unveils Qatari Boeing 747 before joining Air Force One
Iraq wants to increase oil production from the southern fields by 3 million barrels per day within 1-2 months