Boxco Moves Longest Column through Mumbai Port

December 18, 2014

 

Boxco Logistics has set the bar high yet again, by moving the LONGEST COLUMN EVER that was transported in and out of Mumbai Port. It all started in the industrial township of Dahej in the state of Gujarat at ISGEC Heavy Engineering’s manufacturing plant. A massive 91 meter long, 880 MT C2 Splitter column built for a refinery in Mexico, shadowed the workshop buildings

The multimodal logistics, involving engineering and execution of transporting the equipment from Dahej to Mumbai for further export to Mexico, were carried by the team at Boxco Logistics.
Apart from the C2 Splitter, a 380 MT Quench water tower and a 250 MTDemethaniserwere also to be transported along with their accessories.

The transportation of the columns from ISGEC plant to Adani port was a challenge for C2 Splitter which measured 91 m x 9.5 m x 9 m in dimensions. The haulage was meticulously planned in advance, civil works like road widening, removal of obstacles including dividers and light poles were carried out prior commencement of transportation. Electrical HT line shutdowns also had to be arranged the local electricity boards.

In coordination with the local police, the transportation was carried out using state of art remote controlled Scheuerle K25 Self-Propelled Modular Transporters (SPMTs)which is the most advanced hydraulic haulage equipment in the country today.

The team faced a large number of challenges including turning restrictions like dividers road ends and conveyor beltstructures despite the 8 electronic steering modes available onboard the SPMTs.

The transportation of all 3 equipments was carried out in a span of 4 days.The entrance wall to Adani port was razed to move the convoys into its premises. Intra port transportation also posed a challenge due to narrow passages existing especially for the 91 m long C2 Splitter.

The shipment schedule for equipments from Dahej stood on the edge of the harsh ongoing monsoon season. DB Triton Vision under tow by 30 T Bollard Pull MT Canara Progress had been chosen to complete this mammoth task of sea transportation from turbulent waters of the Narmada delta in Gulf of Khambat up to the Port of Mumbai.

After engineering the required stowage plan, executing the jetty civil works and ramp construction. the barge arrived at RORO jetty at Dahej under tow by smaller tugs due to low draft conditions of the Narmada basin.

Logistics News

Smart Port Challenge 2025 Attracts 288 Proposals, Winners Announced

Smart Port Challenge 2025 Attracts 288 Proposals, Winners Announced

Noatum Maritime, Bapco Upstream Sign Agreement for Marine Services at Bahrain LNG Terminal

Noatum Maritime, Bapco Upstream Sign Agreement for Marine Services at Bahrain LNG Terminal

Algoma Central Fleet Hits the 100-Vessel Mark, Records Strong Q3

Algoma Central Fleet Hits the 100-Vessel Mark, Records Strong Q3

Anglo-Eastern Debuts Methanol Bunkering Simulator, Courses

Anglo-Eastern Debuts Methanol Bunkering Simulator, Courses

Subscribe for Maritime Logistics Professional E‑News

Cathay Pacific buys back shares of Qatar Airways worth $897.3 Million
Pembina Pipeline will supply LNG to Malaysian PETRONAS for 20 Years
After Russian strikes, Ukraine imports gas from Greece via the Balkans to keep its system running