Trans Mountain Pipeline to load 22 Tankers in Vancouver

June 12, 2024

© Vladimir / Adobe Stock
© Vladimir / Adobe Stock

Twenty-two oil tankers are scheduled to load this month in Vancouver with crude from the expanded Trans Mountain pipeline, which is running around 80% full with a "little bit" of spot capacity also being used, a Trans Mountain executive said on Wednesday.

Speaking with Reuters six weeks after the C$34.2 billion ($24.94 billion) project started commercial operations, Trans Mountain Corp's chief financial and strategy officer Mark Maki said so far the system is operating as expected and final costs for the expansion are not expected to rise significantly.

The Trans Mountain expansion, which tripled pipeline capacity from Alberta to Canada's Pacific Coast to 890,000 barrels per day (bpd) started commercial operations on May 1 and traders are closely watching flows to gauge demand.

Eighty percent, or 707,000 bpd, of the pipeline's capacity is reserved for long-term contracted shippers, while the remaining 20% is available to spot barrels.

"We're basically running at effectively right around contract level with a little bit of spot on the system," Maki said, adding that volumes were expected to rise towards winter.

Maki said there were 22 tankers scheduled to load at Westridge dock, the pipeline's terminus in the Port of Vancouver, in June.

Traders and shipping sources had been concerned that logistical constraints at the port could limit tanker loadings at Westridge to less than 20 a month.

So far the marine facility is performing well, Maki added, although the company had to work through some start-up issues on one piece of equipment known as a vapor recovery unit, which removes unwanted vapors from crude.

"The dock facility is working as we'd expected. There are a few things of course you've got to break in and get running right, but we're happy with where we're at," Maki said.

The pipeline is owned by the Canadian government, which has been criticized for the cost of the expansion ballooning to nearly five times its 2017 budget estimate.

Maki said post-construction remediation work is still ongoing but Trans Mountain Corp would have a final cost in place by the end of this year and it would likely be "very, very close" to C$34 billion dollars.

He also said it was unlikely Trans Mountain would need to further increase a C$19 billion loan facility agreed with a syndicate of commercial banks and guaranteed by the Canadian government, unless it was for a transitory purpose like issuing bonds.

"If we do it would probably be transitory and not a particularly large increase," Maki said.


(Reuters - Reporting by Nia Williams in British Columbia; Editing by David Gregorio)


Logistics News

HAROPA PORT Achieves Record 2025 Results, Accelerates Green Corridor Strategy

HAROPA PORT Achieves Record 2025 Results, Accelerates Green Corridor Strategy

UTC Enters into Asia-Pacific Market with Singapore Hub

UTC Enters into Asia-Pacific Market with Singapore Hub

Port NOLA Marks Ninth Year Surpassing One Million Cruise Passenger Movements

Port NOLA Marks Ninth Year Surpassing One Million Cruise Passenger Movements

DP World Survey Finds Trade Leaders Upbeat on 2026 Despite Rising Barriers

DP World Survey Finds Trade Leaders Upbeat on 2026 Despite Rising Barriers

Subscribe for Maritime Logistics Professional E‑News

EU to phase out high-risk technology targets Huawei and Chinese companies
The US military has seized another Venezuelan-linked tanker off the Caribbean coast
Ethiopian Airlines orders nine Boeing 787 Dreamliners for long-haul flights