Keppel FELS Delivers First Rig of 2010

January 21, 2010

Keppel FELS Limited (Keppel FELS) has delivered Ensco 8502, the third of seven Ensco 8500 Series semisubmersible (semi) drilling rigs it has been contracted to build exclusively for Ensco International (NYSE:ESV).

Delivered seven days ahead of schedule, Ensco 8502 is on track to commence operations in the U.S. Gulf of Mexico in the second quarter of 2010, under a two-year contract with Nexen Petroleum U.S.A. Inc. with term extension options.

The early completion was a culmination of progressive productivity gains achieved by Keppel FELS on the construction of the Series.

Construction lead time for Ensco 8502 was reduced by 1.1 million man-hours, as compared to the first rig in the Series. This represents a 15% boost in efficiency.

When the Ensco 8500 Series is completed, Keppel-built rigs will make up 30% of the leading driller’s premium fleet. Construction of the next four rigs remains on schedule with expected deliveries extending from the fourth quarter of 2010 into 2012.

Logistics News

US, Australia Sign Critical Minerals Agreement, Back Submarine Deal

US, Australia Sign Critical Minerals Agreement, Back Submarine Deal

Alaska LNG Pipeline Study Will Be Completed This Year

Alaska LNG Pipeline Study Will Be Completed This Year

Maritime Recruitment Webinar: How Much Does "Connectivity" Matter

Maritime Recruitment Webinar: How Much Does "Connectivity" Matter

Russian Wheat Export Prices Climb, Increasing October Estimates

Subscribe for Maritime Logistics Professional E‑News

A basketball-driver is killed after a stone attack on a bus carrying fans in Italy
Australia warns China against 'unsafe flare drops' in an aerial encounter
Phillips 66 and Kinder Morgan are eyeing a new pipeline to boost US West Coast fuel supplies