Ithaca’s FPF-1 platform to be moved to Stella field

July 23, 2016

Ithaca Energy Inc. reports that the "FPF-1" floating production facility has completed the required inclination test as planned and departed the Remontowa shipyard in Gdansk, Poland.

The vessel has been moved to a deep water location offshore Gdansk to undertake final marine system trials over the course of next week. Upon completion of these trials, the FPF-1 will commence the tow to the Stella field. A further update will be provided once towing operations have commenced.
 

Logistics News

Panama Canal Launches Concession Process for Natural Gas Pipeline

Panama Canal Launches Concession Process for Natural Gas Pipeline

South Africa's Transnet Agrees Equipment Deal with Liebherr

South Africa's Transnet Agrees Equipment Deal with Liebherr

Port of Long Beach Orders Two Ship-to-Shore Cranes

Port of Long Beach Orders Two Ship-to-Shore Cranes

MELTRIC Introduces the P66 Industrial Plug and Receptacle

MELTRIC Introduces the P66 Industrial Plug and Receptacle

Subscribe for Maritime Logistics Professional E‑News

Oneworld Alliance looks to India as a partner in its expansion.
LME Zinc stocks indicate tight market but physical supplies are plentiful
Italian deputy PM discusses autos with China amid EU tensions