marine link image

ACP Demands GUPC to Resume Locks Project Work

February 5, 2014

Jorge Quijano
Jorge Quijano

The ACP demanded today that Grupo Unidos por el Canal (GUPC), the consortium in charge of the construction of the third set of locks, resume work on the project as required by the contract. GUPC is formed by the companies Sacyr Vallehermoso, S.A (Spain), Impregilo, S.p.A. (Italy), Jan de Nul Group (Belgium) and Constructora Urbana, S.A. (CUSA) (Panama).

After two weeks of negotiations, which saw production levels drop to 25%, almost all activity has ceased.

The Canal Administrator, Jorge Quijano, stated that ACP continues to try to find a solution, but stressed that the contractor must resume normal activity which is especially crucial during the dry season in Panama.

“ACP continues to keep the door open for a reasonable resolution within the contract,” Quijano reiterated.
 

Logistics News

OPEC+ Responds to Hormuz Shutdown

OPEC+ Responds to Hormuz Shutdown

Vessels Diverted Around Cape of Good Hope

Vessels Diverted Around Cape of Good Hope

At Least Three Tankers Hit in Gulf

At Least Three Tankers Hit in Gulf

Xeneta Weekly Ocean Container Shipping Market Update: February 27, 2026

Xeneta Weekly Ocean Container Shipping Market Update: February 27, 2026

Subscribe for Maritime Logistics Professional E‑News

After US and Israel attack Iran, airlines cancel flights
Dubai gold flow curtailed as flights are halted because of US-Israeli attacks on Iran
Shares of Australian airline Qantas fall by more than 10% after US-Iran conflict