Costa Smeralda to be Delivered a Month Late

September 16, 2019

Citing technical complexities, Meyer Turku is delaying the delivery of the cruise ship Costa Smeralda one month from mid-October to mid-November.

With its new LNG propulsion system and many sophisticated rooms with stage and audio/video equipment the complexity and sophistication of the ship is very high in order to create a unique Costa-style passenger experience. Aside from its unique design features also its size of 180,000 GT is much larger than the recently built ships at Turku shipyard.

In getting this all to work together with many involved persons and companies, Meyer Turku had a slower progress speed than needed.




Logistics News

Next Geosolutions Wins TenneT TSI Contract for North Sea Survey

Next Geosolutions Wins TenneT TSI Contract for North Sea Survey

ABB Introduces Quay Crane Automation Solution

ABB Introduces Quay Crane Automation Solution

Kongsberg Maritime Study Identifies Key Passenger, Freight Routes Across Northern Europe

Kongsberg Maritime Study Identifies Key Passenger, Freight Routes Across Northern Europe

Four NYK Group Managed Vessels Receive Japanese Pilots' Best Quality Ship 2025 Award

Four NYK Group Managed Vessels Receive Japanese Pilots' Best Quality Ship 2025 Award

Subscribe for Maritime Logistics Professional E‑News

French and Benelux stocks: Factors to watch
British Airways extends Middle East flights to August 1,
Airbus targets 10% savings on costs due to global uncertainty and supply problems