Costa Smeralda to be Delivered a Month Late

September 16, 2019

Citing technical complexities, Meyer Turku is delaying the delivery of the cruise ship Costa Smeralda one month from mid-October to mid-November.

With its new LNG propulsion system and many sophisticated rooms with stage and audio/video equipment the complexity and sophistication of the ship is very high in order to create a unique Costa-style passenger experience. Aside from its unique design features also its size of 180,000 GT is much larger than the recently built ships at Turku shipyard.

In getting this all to work together with many involved persons and companies, Meyer Turku had a slower progress speed than needed.




Logistics News

Asia Pacific Ports Collaborate Cross-Sector to Advance Hydrogen, E-Fuel Readiness

Asia Pacific Ports Collaborate Cross-Sector to Advance Hydrogen, E-Fuel Readiness

Russia Adds Four LNG Carriers to Fleet

Russia Adds Four LNG Carriers to Fleet

Two New Post-Panamax Cranes Arrive at Port Tampa Bay

Two New Post-Panamax Cranes Arrive at Port Tampa Bay

U.S. Appeals Court Backs FMC in Evergreen Dispute

U.S. Appeals Court Backs FMC in Evergreen Dispute

Subscribe for Maritime Logistics Professional E‑News

Airline cancels flights due to Middle East conflict
Bangladesh to switch from Airbus to Boeing for jets
DCC rejects a $6.66 billion offer to buy DCC, shares fall