Costa Smeralda to be Delivered a Month Late

September 16, 2019

Citing technical complexities, Meyer Turku is delaying the delivery of the cruise ship Costa Smeralda one month from mid-October to mid-November.

With its new LNG propulsion system and many sophisticated rooms with stage and audio/video equipment the complexity and sophistication of the ship is very high in order to create a unique Costa-style passenger experience. Aside from its unique design features also its size of 180,000 GT is much larger than the recently built ships at Turku shipyard.

In getting this all to work together with many involved persons and companies, Meyer Turku had a slower progress speed than needed.




Logistics News

Singapore Bunker Sales Maintain Strong Start in 2026

Singapore Bunker Sales Maintain Strong Start in 2026

Russia's Taman Port Damaged by Ukrainian Drones

Russia's Taman Port Damaged by Ukrainian Drones

Epstein Files Brings Down DP World Boss

Epstein Files Brings Down DP World Boss

Port Attack Near Odesa Kills Three Brothers

Port Attack Near Odesa Kills Three Brothers

Subscribe for Maritime Logistics Professional E‑News

Dubai's DP World chief removed from position after pressure on Epstein
Travel groups and airlines warn about the impact of a partial shutdown of government on airport screening
Trump: Iran regime change is a 'best thing,' says second carrier heading to Middle East