Costa Smeralda to be Delivered a Month Late

September 16, 2019

Citing technical complexities, Meyer Turku is delaying the delivery of the cruise ship Costa Smeralda one month from mid-October to mid-November.

With its new LNG propulsion system and many sophisticated rooms with stage and audio/video equipment the complexity and sophistication of the ship is very high in order to create a unique Costa-style passenger experience. Aside from its unique design features also its size of 180,000 GT is much larger than the recently built ships at Turku shipyard.

In getting this all to work together with many involved persons and companies, Meyer Turku had a slower progress speed than needed.




Logistics News

Short-Term Tanker Market Shaken Up by Geopolitics

Short-Term Tanker Market Shaken Up by Geopolitics

Panama Canal, USGBC Sign MOU to Enhance US Agricultural Trade

Panama Canal, USGBC Sign MOU to Enhance US Agricultural Trade

Greg Baribault Appointed as President of Enstructure Northeast

Greg Baribault Appointed as President of Enstructure Northeast

Blue Water Announces Andy Tite as Senior Vice President, Projects

Blue Water Announces Andy Tite as Senior Vice President, Projects

Subscribe for Maritime Logistics Professional E‑News

Extra Space Storage sued for 'predatory practices' by New York City
Dubai's DXB Airport is expected to handle 100 million passengers in this year
US investigation finds no evidence of spyware on Chinese power inverters