Costa Concordia Salvage Update

April 23, 2013

Costa Concordia 1st Sponson: Photo credit Parbuckling Project
Costa Concordia 1st Sponson: Photo credit Parbuckling Project

Salvors have successfully positioned the first port-side sponson that will be used in the 'parbuckling' stage of the wreck removal process.

Operations now continue with the installation of the second sponson, and eventually they will be welded on the hull of the wreck.

At the same time,  drillings for next 10 underwater holes will carry on in order to position remaining platforms 2 & 3.

In this major feat of salvage and underwater engineering altogether 438 workers based at Giglio are currently engaged in operations to float the wrecked cruise ship and tow it away.

Logistics News

Contship Introduces First Electric Port Tractor into Operations

Contship Introduces First Electric Port Tractor into Operations

ABS, HD KSOE Collaborate for Digital Shipbuilding, Vessel Intelligence

ABS, HD KSOE Collaborate for Digital Shipbuilding, Vessel Intelligence

UTC Overseas, Transoceanic Launch US Gulf Coast Logistics Joint Venture

UTC Overseas, Transoceanic Launch US Gulf Coast Logistics Joint Venture

US Container Imports Fall 3.2% in April, Descartes Reports

US Container Imports Fall 3.2% in April, Descartes Reports

Subscribe for Maritime Logistics Professional E‑News

Enbridge, a Canadian gas transmission company, tops the profit estimates for its strength.
Maguire: Seven markets to watch if the Middle East is at peace.
Sweden cancels plans to build a power cable from Denmark due to disagreements with EU funding plan