Australia Pacific LNG Reaches Curtis Island

February 12, 2015

Australia Pacific LNG today announced it had reached a significant milestone with the arrival of first gas from its coal seam gas fields in the Surat Basin to its liquefied natural gas (LNG) facility on Curtis Island, near Gladstone, Queensland.

The arrival of the first gas into the LNG facility also marks the completion of commissioning of the 530km high pressure gas pipeline, another important milestone for the project.

With the completion of the pipeline and the arrival of the gas, Australia Pacific LNG can initiate the commissioning of the power generation facilities on the island.

The commissioning phase of the LNG facility also includes the verification and testing of each system of the first processing train and the two LNG tanks; part of which has already commenced.

Page Maxson, CEO Australia Pacific LNG, said: “The achievement of two major milestones, first gas to Curtis Island and completion of commissioning of the pipeline, demonstrates continued strong progress by Australia Pacific LNG and paves the way for the commissioning of the power generation facilities on the island.

“These milestones have been achieved thanks to the incredible effort by the many people committed to safely delivering the Australia Pacific LNG project.

“Australia Pacific LNG looks forward to completing the final phase of construction and delivering first LNG in mid-2015.”


 

Logistics News

Dual Pre-FEED Wins Propel ECOnnect’s LNG IQuay Regas Terminal

Dual Pre-FEED Wins Propel ECOnnect’s LNG IQuay Regas Terminal

Burger Boat Company Announces Promotion of Ron Cleveringa

Burger Boat Company Announces Promotion of Ron Cleveringa

Pedro Widmann Joins UTC Overseas

Pedro Widmann Joins UTC Overseas

SRI Study Shows a Growing Number of Countries Implementing Cabotage Laws

SRI Study Shows a Growing Number of Countries Implementing Cabotage Laws

Subscribe for Maritime Logistics Professional E‑News

Brunei enables China-made jets to boost COMAC
Trans Mountain pipeline and Canada oil shippers are in discussions to resolve the shipping cost dispute
Tesla recalls 63,000 Cybertrucks due to lighting defects, fixes software