Water Levels to Be Lowered for Lock and Dam 1 Repairs

Wednesday, June 21, 2023

The U.S. Army Corps of Engineers, St. Paul District, and Minnesota Department of Natural Resources plan to slightly lower the Mississippi River between Lower St. Anthony Falls and Lock and Dam 1, both in Minneapolis, starting June 24.

Corps officials plan to maintain the lower river elevations through July 7, to inspect and repair the rubber dam on top of the spillway at Lock and Dam 1. To access the rubber dam, the water levels will be lowered approximately one foot below the spillway crest for approximately two weeks. 

Once the repairs are complete, the normal water levels are expected to be restored no later than July 9.

Navigation will remain open to the public during maintenance.

Categories: Infrastructure

Related Stories

NYK Group’s ICO Launches Belgium’s First Shore Power Facility for RoRo Ships

New Zealand selects two LNG terminal bidders for energy security

New Quay Cranes Boost Baltic Container Terminal's Capabilities

Current News

How JobMarineMan Is Building a Direct Crew Recruitment Ecosystem

Baltic Index Reaches One-Week High on Higher Capesize Rates

NYK Group’s ICO Launches Belgium’s First Shore Power Facility for RoRo Ships

BMT, Austal Sign Engineering Alliance to Support Shipbuilding Projects

Subscribe for Maritime Logistics Professional E‑News