Cheniere to Roll Out Second LNG Unit

By Aiswarya Lakshmi
Thursday, May 26, 2016

 Cheniere Energy Inc. plans to start exporting liquefied natural gas in August from a second plant at its Sabine Pass terminal in Cameron Parish, according to a report from Bloomberg News. 

Cheniere began exporting LNG in February from its first unit at Sabine Pass. In its fourth-quarter report, Cheniere said the second unit could begin producing LNG by mid-2016. 
When completed, the Sabine Pass facility will have six LNG units. The first two units have a combined production capacity of 9.9 million tons LNG per year.
“Actual project progress supports the achievement of substantial completion for Trains 1 and 2 by late May 2016 and September 2016, respectively," the company said in the filing with the Federal Energy Regulatory Commission.
Categories: Ports LNG Logistics

Related Stories

TotalEnergies, OQEP Start Construction of Marsa LNG Plant in Oman

Fincantieri, Accenture Launch JV for Cruise, Defense and Ports Digitalization

Australian Regulator Greenlights Qube's RoRo Terminal Deal

Current News

Panama Canal Administrator Outlines the Waterway’s Evolving Role in Global Trade

Pembrokeshire College: Curriculum Development Manager Recognized for Contributions

USTR Port Fees Contrasted With Supply Growth Sound the Alarm for Car Carriers in 2026/27

Aptamus Picks Aker Solutions’ Entr for LCO2 Terminal Engineering

Subscribe for Maritime Logistics Professional E‑News