Cheniere to Roll Out Second LNG Unit

By Aiswarya Lakshmi
Thursday, May 26, 2016

 Cheniere Energy Inc. plans to start exporting liquefied natural gas in August from a second plant at its Sabine Pass terminal in Cameron Parish, according to a report from Bloomberg News. 

Cheniere began exporting LNG in February from its first unit at Sabine Pass. In its fourth-quarter report, Cheniere said the second unit could begin producing LNG by mid-2016. 
When completed, the Sabine Pass facility will have six LNG units. The first two units have a combined production capacity of 9.9 million tons LNG per year.
“Actual project progress supports the achievement of substantial completion for Trains 1 and 2 by late May 2016 and September 2016, respectively," the company said in the filing with the Federal Energy Regulatory Commission.
Categories: LNG Logistics Ports

Related Stories

Ukraine Says Russian Drone Attack Hit Civilian Vessel

MSC, BlackRock's Bid for Hutchison's Barcelona Terminal May Raise Prices

Brazil Court Recommends Auction of Santos Terminal

Current News

ICTSI to Operate Durban Container Terminal Pier 2

Celebrity Edge Makes Maiden Call to Newcastle, Australia

Ukraine Says Russian Drone Attack Hit Civilian Vessel

Bulk Carrier on Fire After Russian Attack

Subscribe for Maritime Logistics Professional E‑News