US Aircraft Carrier Overhaul Deferred

Press Release
Sunday, February 10, 2013

The aircraft carrier USS Abraham Lincoln's refueling complex overhaul (RCOH) will not start due to insufficient funding.

Lincoln was expected to move to Newport News shipyard next week to begin the overhaul. However, as a result of the fiscal constraints resulting from the ongoing continuing resolution (CR), the contract for the refueling complex overhaul (RCOH) has not been issued to Huntington Ingalls Industries, Inc. 



The aircraft carrier will remain pierside at Naval Station Norfolk until sufficient funding is received to start the execution of the RCOH. In the meantime, the ship's Sailors continue to conduct maintenance.



The impact of postponing CVN 72's RCOH is three-fold:  the time scheduled for the RCOH will have to be lengthened because the overhaul will not begin when it was expected; delayed redelivery of Lincoln to the fleet,
 as well as its impact upon industry.

The Navy add that cancelling or delaying maintenance creates a significant backlog of deferred maintenance and affects future year schedules and costs, as well as future readiness. The delay in Lincoln's RCOH will affect other carrier work.

Categories: Legal Ship Repair & Conversion Navy Finance Eye on the Navy

Related Stories

Worley Secures Work on German LNG Terminal

Crowley to Install LNG-Fueled Microgrid at Puerto Rico Terminal

Port & Terminal Technology USA Set for Miami

Current News

DP World, Asian Terminals Inc. Invest $100M to Boost Capacity at Manila South Harbor

PD Ports Outlines Plans to Develop UK Offshore Wind Hub

DP World Begins $165 Million Expansion of Maputo Container Terminal Capacity

Port Canaveral Invests $500 Million in Five-Year Port-Wide Improvement Plan

Subscribe for Maritime Logistics Professional E‑News