Is This a Record? Three Monopiles Installed in 35 Hours

April 21, 2013

Seajacks Zaratan Placing Monopile
Seajacks Zaratan Placing Monopile

Specialised subsea construction jack-up vessel 'Seajacks Zaratan' continues installation at a rapid pace at the North Sea Meerwind Offshore Park.

Seajack Zaratan collected the three 675t steel structures from the construction port of Cuxhaven on the evening of Thursday 11th April. After completing the 110km transit to the German Bight site in 7 hours, Zaratan was jacked up at the first location ready to commence operations on Friday lunchtime and had completed hammering of the third pile by midnight on Saturday, resulting in a net installation time of 35 hours.

The subsea construction vessel is currently in port loading the last batch of monopiles, which will conclude this phase of construction. The owners say that such an impressive performance by the new installation vessel and its experienced crew means that monopile installation is scheduled to be completed on schedule by the end of April.

 

Logistics News

DP World, Asian Terminals Inc. Invest $100M to Boost Capacity at Manila South Harbor

DP World, Asian Terminals Inc. Invest $100M to Boost Capacity at Manila South Harbor

PD Ports Outlines Plans to Develop UK Offshore Wind Hub

PD Ports Outlines Plans to Develop UK Offshore Wind Hub

DP World Begins $165 Million Expansion of Maputo Container Terminal Capacity

DP World Begins $165 Million Expansion of Maputo Container Terminal Capacity

Port Canaveral Invests $500 Million in Five-Year Port-Wide Improvement Plan

Port Canaveral Invests $500 Million in Five-Year Port-Wide Improvement Plan

Subscribe for Maritime Logistics Professional E‑News

Adani Ports in India beats its quarterly profit forecast on the back of higher cargo growth
Cargill and LDC among the winners of Brazil's port auction
Data and sources say that the last Chevron chartered vessel is returning oil cargo to Venezuela.