Panama Canal Wait Times Back to Normal

Posted by Eric Haun
Monday, November 30, 2015
Waiting times for ships at the Panama Canal have returned to normal after poor weather and a spike in traffic caused delays for several weeks, the waterway's operator said on Monday.
"Today ... the line is 45 ships, which represents a maximum waiting time of two days," the Panama Canal Authority (ACP) said in a statement, noting that better weather and extra funding aimed at freeing up the traffic had reduced the bottleneck.
The ACP said the problems caused delays of more than 10 days in October and though they were easing by-mid November, the delays were beyond the 24-to-36 hour normal waiting times.
Tracking systems showed that at the height of the delays, more than 130 ships were held up at the canal's two anchorages, prompting some companies to complain.


(Reporting by Elida Moreno; Editing by Jeffrey Benkoe)
Categories: Logistics Navigation Ports

Related Stories

Great Lakes Dredge & Dock Takes Delivery of Hopper Dredge

Infrastructure Projects Continue at Port of Charleston

AAPA Writes to DOT about Surface Transportation Reauthorization

Current News

Baltic Index Rises, Sees Gains Across All Vessel Sizes

Cuba Maritime & Port Celebrates Three Years of Industry Innovation and Collaboration

Melvin Resigns as President of South Carolina Ports Authority

Brazil Ships More Iron Ore to China, Competitors Lag

Subscribe for Maritime Logistics Professional E‑News