Fairway Dredging Project Remains on Track

Laxman Pai
Wednesday, November 20, 2019

Port of Hamburg is continuing its dredging projects on the Elbe River as per plan. The second hopper dredger named Bonny River has been conducting dredging operations on the federal stretch and taking the spoil to the UWA - underwater dredged material disposal site at Medemrinne, from October.

Built in 2018, the ‘Bonny River’ has a hold capacity of over 16,000 cubic meters; consequently having a highly efficient performance level.

The holding area near Brunsbüttel and the widening work on the WSV - federal waterways and shipping stretch are finished. With the widening from 300 to 320 meters from Wedel to down river from the mouth of the River Stör, ships with a combined width of 92 meters can now pass each other.

The hopper dredger ‘Scheldt River’ started completion work (deepening) at the beginning of October. The fairway on the federal WSV stretch will be deepened by an average of one metre. The UWA sites at Brokdorf, Medemrinne, Neufelder Sand and St. Margarethen are already completed, so that they can receive the spoil.

Now, the last of the UWA sites at Scheelenkuhlen is currently being set up. The surrounding wall has a length of approx. 2,600 metres.

In total, some 878,000 tons of spoil mixture will be deposited here. This site has a capacity of approx. 1.7 million cubic metres for the spoil from Schwarztonnensand at the Lateral Elbe.

Firstly, the ‘Bonny River’ is preparing the WSV part of the passing box. This box has a width of 385 metres, facilitating oncoming traffic of up to four mega-containerships. This work will be completed by the end of the year, so that from the very start of the coming year, on this stretch shipping will feel the first benefit in passing traffic. However, the full benefits of the passing box’s complete use will not emerge until all dredging is finished in 2021.

Comprehensive ecological projects are part of the fairway adjustment too, with the federal government investing a total of 75 million euros. The earth-moving work in Lower Saxony on the island of Schwarztonnensand as well as on various polders on the River Stör in Schleswig-Holstein have been completed.

The dredging work for the most extensive aquatic nature protection measures at Schwarztonnensand/Lateral Elbe, contracted out together with construction of the UWA Scheelenkuhlen, will start in spring 2020.

Categories: Ports Dredging Vessels Coastal/Inland Dredger

Related Stories

Port Houston Surpasses Three Million TEUs

Fueling the Future of Ports: Cost Savings and Resilience as Propane’s Proven Edge

GCMD and IAPH Forge Decarbonization Coalition Across Global Ports

Current News

Millions of Cigarettes Seized in Multi-Nation Operation

Liebherr USA Appoints New Divisional Director

Port Houston Surpasses Three Million TEUs

Trump, Xi Pause Port Fees on Each Other's Vessels

Subscribe for Maritime Logistics Professional E‑News