Panama Canal PAC-4 Work Begins

Tuesday, January 26, 2010

Work on the second largest contract of the Panama Canal Expansion Program has begun. The Panama Canal Authority (ACP) issued consortium FCC-ICA-Meco the Notice to Commence the fourth and final dry excavation (PAC-4) contract.

PAC-4 is the most complex expansion project after the design and build of the new set of locks. The dry excavation included in PAC-4 will create an access channel linking the new Pacific locks with the Canal's existing Gaillard Cut (the narrowest stretch of the Panama Canal).

The ACP awarded the PAC-4 contract to FCC-ICA-Meco, a Spanish, Mexican and Costa Rican joint venture, following the consortium's lowest bid submission of $267.8m and its compliance with the requirements established in the request for proposal specifications. The ACP issued the Notice after receiving FCC-ICA-Meco's performance and payment bonds and signing the contract.

The scope of work will include 26 million cubic meters of unclassified excavation, the installation of a backfilled cellular cofferdam water barrier and the construction of an earth-rock filled dam that will create part of the access channel's eastern bank. The work is scheduled to conclude during the third quarter of 2013.

Expansion will build a new lane of traffic along the Panama Canal through the construction of a new set of locks which will double capacity and allow more traffic and longer, wider ships.


Related Stories

9,000 m³ Methanol-ready Tanker Christened

Charlie Cunnion Named as Massport Port Director

GT Wings Launches Lightweight AirWingS

Current News

Baltic Index Hits Third Weekly Loss As Capesize Rates Remain Weak

European Wheat Falls Alongside Shifts in the Euro, Russian Exports

Oil Supertanker Rates Drop After Record Highs

DP World Busan Deploys Electric Yard Tractors

Subscribe for Maritime Logistics Professional E‑News