Panama Canal Locks Project Work Resumes

Posted by Michelle Howard
Friday, February 21, 2014

The Panama Canal Authority (ACP) said that Grupo Unidos por el Canal. S.A. (GUPC) has resumed work on the new locks project during the afternoon of Thursday, February 20.

“Works have restarted this afternoon,” said Panama Canal Administrator Jorge L. Quijano. “The consortium has guaranteed that it will continue working, which was our main objective so we can move forward and discuss other issues for a longer-term agreement.”

Since works have resumed, ACP will proceed to pay tomorrow GUPC the $36.8 million due for December invoices. 

This preliminary agreement to resume works does not imply a negotiation on the alleged cost overruns claimed by the contractor. ACP reiterates that these claims must be process through the mechanisms within the contract.

The consortium is formed by Sacyr Vallehermoso, S.A (Spain), Impregilo, S.p.A. (Italy), Jan de Nul Group (Belgium) and Constructora Urbana, S.A. (CUSA) (Panama).

The parties will continue to negotiations during the next couple of days to come to an agreement that ensures the successful completion of the project.

Categories: Contracts Finance Government Update Ports

Related Stories

IFM Investors Fund to Acquire Majority Stake in Associated British Ports

Recent Developments Strengthen Port of Gothenburg RoRo Terminal

From Ports to Power Plants: Decision Intel Transforms Critical Infrastructure

Current News

Port of Los Angeles Reports Record Low Emissions

Import Window for Brazil Ethanol to Reopen in January

Citi: Oil Prices Remain Unstable Despite Recovering Gulf Exports

Asian Imports of LNG to Increase Despite Rising Costs

Subscribe for Maritime Logistics Professional E‑News