The Great Lakes St. Lawrence Seaway System as amended a Planned Outage at Lock 7.

Mariners are advised of a revision to the preplanned closure at Lock 7 for the replacement of Gates 1 and 2. Due to environmental conditions, the closure will begin one day later. The details are as follows:

  • Dates: January 6, 7, 8 and 9, 2025
  • Time: 08:00 to 18:00 each day (10-hour window)
  • During these periods, the lock will be unavailable for transit.

Any deviation from the above schedule will be communicated via major delay communication.

Categories: Ports Government Update Great Lakes Coastal/Inland Regulation Infrastructure Marine Safety

Related Stories

Dajin, Zima Plan Offshore Wind Foundations Plant at Spain's Gijon Port

Panama Court Quashes CK Hutchison Port Contracts

Inland Waterways Infrastructure: The Time is Now

Current News

Columbia Group Appoints Prevention at Sea as Compliance Partner

Contecon Manzanillo Surpasses 12 Million TEUs

Hydrex Conducts Underwater Repair of Bent Container Ship Propeller

HHLA Container Terminal Orders Eight Hybrid Konecranes Straddle Carriers

Subscribe for Maritime Logistics Professional E‑News