UK Giant Offshore Wind Farm Cable Installation Complete

Press Release
Friday, October 26, 2012

Array cable installation completed at London Array by a small fleet of specialised vessels.

Six days after the final foundation was installed at London Array the project has achieved another milestone – all array cables have now been installed at the offshore site.

The installation of the last array cable was completed recently by the Normand Flower. Altogether, 187 cables have been installed by a combination of vessels – Jan Steen, Stemat 82, Stemat Oslo, Normand Flower and the Pontra Maris.

This major UK offshore wind farm project is due for completion by the end of 2012 and includes:

    •    An offshore area of 100km2
    •    175 wind turbines
    •    Two offshore substations
    •    Nearly 450km of offshore cabling
    •    One onshore substation
    •    630MW of electricity
    •    Enough power for over 470,000 homes a year – two thirds of the homes in Kent
    •    CO2 savings of 925,000 tonnes a year
 

Categories: Offshore Technology Wind Power

Related Stories

ADNOC L&S, Borouge Sign $531M Partnership to Boost UAE Petrochemical Exports

GravityVibe in Action: Self-Unloader Optimized

Singapore and France Partner on Bio-LNG

Current News

Mitsui OSK: Shipping in the Gulf Continues, Closely Monitoring Situation

Marine Fuel Sales at Fujairah Port Hit Three-Month Low

ContainerWheels 2-in-1: Patented System Aims to Simplify Container Handling

Shipbuilding: ONE Singapore Joins the Fleet

Subscribe for Maritime Logistics Professional E‑News