Is This a Record? Three Monopiles Installed in 35 Hours

Press Release
Sunday, April 21, 2013

Specialised subsea construction jack-up vessel 'Seajacks Zaratan' continues installation at a rapid pace at the North Sea Meerwind Offshore Park.

Seajack Zaratan collected the three 675t steel structures from the construction port of Cuxhaven on the evening of Thursday 11th April. After completing the 110km transit to the German Bight site in 7 hours, Zaratan was jacked up at the first location ready to commence operations on Friday lunchtime and had completed hammering of the third pile by midnight on Saturday, resulting in a net installation time of 35 hours.

The subsea construction vessel is currently in port loading the last batch of monopiles, which will conclude this phase of construction. The owners say that such an impressive performance by the new installation vessel and its experienced crew means that monopile installation is scheduled to be completed on schedule by the end of April.

 

Categories: Offshore Offshore Energy Underwater Engineering Wind Power

Related Stories

Tanker Bound for Cuba with Fuel Cargo Diverts to Trinidad

PERC Leads Fuel Conversation at Port of the Future Conference

Energy Flow Stressed with Fujairah Port, Shah Gas Field Attacks

Current News

Argentina Grain Exports Rise From Strong Harvest

Tanker Bound for Cuba with Fuel Cargo Diverts to Trinidad

Independent Port Consultants Announces New Hires

US Crude Being Shipped to Asia Via Panama Canal

Subscribe for Maritime Logistics Professional E‑News