Is This a Record? Three Monopiles Installed in 35 Hours

Press Release
Sunday, April 21, 2013

Specialised subsea construction jack-up vessel 'Seajacks Zaratan' continues installation at a rapid pace at the North Sea Meerwind Offshore Park.

Seajack Zaratan collected the three 675t steel structures from the construction port of Cuxhaven on the evening of Thursday 11th April. After completing the 110km transit to the German Bight site in 7 hours, Zaratan was jacked up at the first location ready to commence operations on Friday lunchtime and had completed hammering of the third pile by midnight on Saturday, resulting in a net installation time of 35 hours.

The subsea construction vessel is currently in port loading the last batch of monopiles, which will conclude this phase of construction. The owners say that such an impressive performance by the new installation vessel and its experienced crew means that monopile installation is scheduled to be completed on schedule by the end of April.

 

Categories: Offshore Offshore Energy Underwater Engineering Wind Power

Related Stories

US Commerce Disorganization Stalls Thousands of Export Approvals

BSM Launches Methanol Bunkering Simulator

TotalEnergies, CMA CGM to Form LNG Bunkering Logistics JV

Current News

US Commerce Disorganization Stalls Thousands of Export Approvals

Russian Oil Vessels Forced to Divert From India Under US Sanctions

Hanseatic Global Terminals Launches Latin America Expansion

Two CK Hutchison-Operated Ports Near Panama Could See State Partnerships Take Over

Subscribe for Maritime Logistics Professional E‑News