Production at Cheniere Energy's Sabine Pass liquefied natural gas (LNG) export plant in Louisiana is running well below capacity, resulting in disruption to cargo loadings, trade sources said.

Feed gas supply into the liquefaction plant plunged sharply during the weekend, data on the Thomson Reuters Eikon terminal showed.

Flows fell to 630 million cubic feet/day on Jan. 19 from 3.2 billion cubic feet/day on Jan. 15.

Freezing weather may have disrupted water supply to Sabine Pass, market sources said.

Several production units, or trains, are estimated to be offline, potentially delaying cargo loadings and deliveries to Asian markets in February and March, they said.

Cheniere Energy was not immediately available to comment.


Reporting by Oleg Vukmanovic and Jessica Jaganathan
Categories: Energy Fuels & Lubes LNG Tankers

Related Stories

Barbara Scheel Agersnap Steps Down as Copenhagen Malmö Port CEO

LNG Bunker Vessel Christened

Glenfarne signs 20-year LNG contract with POSCO in South Korea

Current News

Baku Port Handles 37% More Containers in 2025

International Flag-State Association Looks to Advancing Role in Policymaking

The Northwest Seaport Alliance Retires Two Legacy Cranes from Terminal 7

Barbara Scheel Agersnap Steps Down as Copenhagen Malmö Port CEO

Subscribe for Maritime Logistics Professional E‑News