Roll Group Expands Heavy Gantry Capability in Indonesia

Thursday, July 25, 2024

Roll Group has successfully executed two lifts, each exceeding 1,000 tonnes, utilizing its new RMG modular gantry crane system at a Petrochemical Facility in Cilegon, Indonesia.

The implementation of Roll Group's heavy gantry crane system represents a leap forward in the company's ability to install very heavy loads, weighing up to 3,000 tonnes and heights exceeding 120 meters. What sets this system apart is its ability to operate without the need for guy wires, minimizing disruptions to surrounding areas while maximizing efficiency, says Roll Group.

Within the scope of the Cilegon project, Roll Group's scope includes discharging the incoming vessels, transport of all cargo within the facility and lifting the cargo into position.

The project represents a total transport solution, including engineering, project management and the utilization of SPMT’s and five crawler cranes.

Roll Group has started the fabrication of a second gantry system which will be ready for use by the end of 2024.

Categories: Infrastructure Cranes

Related Stories

Port of Auckland Commences Upgrade of Bledisloe North and Fergusson North Wharves

DOE Grants Lake Charles LNG Additional Time to Commence Exports

The Pasha Group Acquires Assets of MacMillan-Piper LLC, Tacoma Transload LLC

Current News

Turkey Bars Israeli Ships From Its Ports

Eighth Island Class Vessel Joins BC Ferries

Vattenfall Secures Dutch Base to Support Germany’s Largest Offshore Wind Farm

Tanker Vessel Market Bends Under Supply and Demand Strains

Subscribe for Maritime Logistics Professional E‑News