Repairs to Mumbai Port's Lock Gate

By Joseph R. Fonseca
Tuesday, November 11, 2014

Mumbai Port Trust in their circular No. MbPT Circular No. TM/ID/CIRCULAR/678  has informed about their plan to repair the outer lock gate through a private contractor. 

The schedule is as under :-
 
Removal of the lock gate on 15th May during day by Port floating crane Shresta, this operation will be from 15th to 20th and resulting in no movements during day ie from 0800 hrs to 1800 hrs from 15th May to 13th September, Indira Dock will be tidal.
 
Since Indira Dock being tidal navigation is possible only during flood tide, which will result in restriction of vessel to loa 152 meters and beam 22.86 meters . There could be only 2/3 movements in each tide and maximum permissible draft will be reduced to 8 mtrs, higher draft will be considered, depending  on tide.
 
The officers of CME, DC/ SDM and Dy Traffic Manger is working on the finer aspects and will issue a circular  within today.
 
Shipping agents association other port users were persuading the port to postpone this repairs, as Traffic Dept and DC department were not in favor  this repairs in monsoon but due to financial implication the Port Chairman has not agreed.
 
As a result of the repairs to the lock gate congestion can be expected at Harbour wall berths.

Categories: Legal Ports Navigation Marine Materials Marine Equipment Maritime Safety Vessels

Related Stories

USTR Implements Port Fee Proposal

NTSB Calls for Better Preparedness of Land-Based Firefighters

US Targets China Oil Storage Terminal in Iran-Related Sanctions

Current News

Swire Shipping Bans Carriage of Donkey Skins

Vietnamese Imports From China and Export to US Reach Record High

BIMCO: Brazilian Grain Shipments Up 9% as China Seeks US Alternative

HD Hyundai and Maersk Cooperate on Decarbonization and Logistics

Subscribe for Maritime Logistics Professional E‑News