US Permit Crackdown Poses New Hurdles for Proposed LNG Projects

By Curtis Williams
Thursday, May 11, 2023

The U.S. Department of Energy's refusal to grant export permit extensions to liquefied natural gas (LNG) developers that fail to meet a construction deadline poses a new hurdle for greenfield plants, analysts said on Thursday.

The DOE last month said it would grant future extensions solely on extenuating circumstances and rejected an extension for Energy Transfer's proposed Lake Charles LNG project.

The change will fall heavily on firms without a track record and available financing, analysts said.

Around a dozen LNG projects in the U.S. and Mexico that would process more than 20 billion cubic feet per day (bcfd) of exports now face difficulties moving forward because of the change, according to an analysis from consultants Rapidan Energy Group.

Without extensions to obtain non-Free Trade Agreement permits, financing for new entrants could dry up, and "for many of these projects, it looks like 'game over,'" said Alex Munton, Rapidan's Global Gas Service director.

Glenfarne Group, which has two plants - Texas LNG and Magnolia LNG - on Rapidan's list of at-risk projects, said it is confident the DOE ultimately will provide extensions.

"Both projects represent exactly the type of forward-thinking environmentally sensitive model the DOE wants for U.S. gas exports in any form,” a Glenfarne spokesperson said.

Energy Transfer appealed the rejection of its permit extension, but has had one customer considering whether to go elsewhere, co-CEO Marshall McCrea told analysts this month.

However, the decision was welcomed by firms with established customers and operations.

Cheniere Energy Inc and Venture Global LNG, which have been able to regularly build new plants, praised the decision.

"Fully commercialized LNG projects, including Cheniere’s, have been constructed and have commenced exports within the seven-year deadline," a Cheniere spokesperson noted.

"We view this development as favorable to Venture Global, given our typical construction schedule,” said Shaylyn Hynes, a spokeswoman for Venture Global LNG, which has consistently beat the seven-year window.


(Reuters - Reporting by Curtis Williams; Editing by Marguerita Choy)

Categories: Tankers Ports LNG Government Update North America Infrastructure Americas Liquid Bulk

Related Stories

Irish Consultancy Opens Its Doors for Offshore Wind, Subsea Markets

Iran's Strait Authority to Facilitate Passage Through Hormuz

New Quay Cranes Boost Baltic Container Terminal's Capabilities

Current News

How JobMarineMan Is Building a Direct Crew Recruitment Ecosystem

Baltic Index Reaches One-Week High on Higher Capesize Rates

NYK Group’s ICO Launches Belgium’s First Shore Power Facility for RoRo Ships

BMT, Austal Sign Engineering Alliance to Support Shipbuilding Projects

Subscribe for Maritime Logistics Professional E‑News