Keppel FELS Delivers First Rig of 2010

Thursday, January 21, 2010

Keppel FELS Limited (Keppel FELS) has delivered Ensco 8502, the third of seven Ensco 8500 Series semisubmersible (semi) drilling rigs it has been contracted to build exclusively for Ensco International (NYSE:ESV).

Delivered seven days ahead of schedule, Ensco 8502 is on track to commence operations in the U.S. Gulf of Mexico in the second quarter of 2010, under a two-year contract with Nexen Petroleum U.S.A. Inc. with term extension options.

The early completion was a culmination of progressive productivity gains achieved by Keppel FELS on the construction of the Series.

Construction lead time for Ensco 8502 was reduced by 1.1 million man-hours, as compared to the first rig in the Series. This represents a 15% boost in efficiency.

When the Ensco 8500 Series is completed, Keppel-built rigs will make up 30% of the leading driller’s premium fleet. Construction of the next four rigs remains on schedule with expected deliveries extending from the fourth quarter of 2010 into 2012.

Categories: Offshore Shipbuilding

Related Stories

Chinese Sanctions on Hanwha Put $150B South Korea-US Shipbuilding Plan at Risk

China Sanctions Five US-Linked Units of South Korea’s Hanwha Ocean

Uncertainty Mounts as U.S. Port Fees on Chinese-Built Ships Near Deadline

Current News

Maritime Recruitment Webinar: How Much Does "Connectivity" Matter

Russian Wheat Export Prices Climb, Increasing October Estimates

September U.S. Container Imports Contract Amid Tariff Uncertainty

Poland Eyes Bids to Expand Floating LNG Terminal

Subscribe for Maritime Logistics Professional E‑News