Keppel FELS Delivers First Rig of 2010

Thursday, January 21, 2010

Keppel FELS Limited (Keppel FELS) has delivered Ensco 8502, the third of seven Ensco 8500 Series semisubmersible (semi) drilling rigs it has been contracted to build exclusively for Ensco International (NYSE:ESV).

Delivered seven days ahead of schedule, Ensco 8502 is on track to commence operations in the U.S. Gulf of Mexico in the second quarter of 2010, under a two-year contract with Nexen Petroleum U.S.A. Inc. with term extension options.

The early completion was a culmination of progressive productivity gains achieved by Keppel FELS on the construction of the Series.

Construction lead time for Ensco 8502 was reduced by 1.1 million man-hours, as compared to the first rig in the Series. This represents a 15% boost in efficiency.

When the Ensco 8500 Series is completed, Keppel-built rigs will make up 30% of the leading driller’s premium fleet. Construction of the next four rigs remains on schedule with expected deliveries extending from the fourth quarter of 2010 into 2012.

Categories: Offshore Shipbuilding

Related Stories

Russian Oil Vessels Forced to Divert From India Under US Sanctions

TotalEnergies, CMA CGM to Form LNG Bunkering Logistics JV

New BIMCO Clause Addresses USTR Actions

Current News

US Commerce Disorganization Stalls Thousands of Export Approvals

Russian Oil Vessels Forced to Divert From India Under US Sanctions

Hanseatic Global Terminals Launches Latin America Expansion

Two CK Hutchison-Operated Ports Near Panama Could See State Partnerships Take Over

Subscribe for Maritime Logistics Professional E‑News