Ithaca’s FPF-1 platform to be moved to Stella field

By Joseph R. Fonseca
Saturday, July 23, 2016

Ithaca Energy Inc. reports that the "FPF-1" floating production facility has completed the required inclination test as planned and departed the Remontowa shipyard in Gdansk, Poland.

The vessel has been moved to a deep water location offshore Gdansk to undertake final marine system trials over the course of next week. Upon completion of these trials, the FPF-1 will commence the tow to the Stella field. A further update will be provided once towing operations have commenced.
 

Categories: Energy Marine Equipment Maritime Safety Offshore Energy Shipbuilding Technology Underwater Engineering Vessels

Related Stories

ClassNK SOF for ‘Seawing’ Automated Kite System

Cruise Shipping: Seatrade Cruise Global Debuts Wellness Oasis

Towage Giant Delivers Record Results, Eyes Global Expansion

Current News

Argentina Grain Exports Rise From Strong Harvest

Tanker Bound for Cuba with Fuel Cargo Diverts to Trinidad

Independent Port Consultants Announces New Hires

US Crude Being Shipped to Asia Via Panama Canal

Subscribe for Maritime Logistics Professional E‑News