NE England Shipyard Completes Cableship Conversion Work

Press Release
Wednesday, August 1, 2012

Global Marine Systems Energy contracted A&P North East to ready 'Cable Enterprise' for offshore wind farm operations.

The project took 110 days work to make the vessel ready for a contract on the Gwynt y Mor offshore wind farm, situated off the coast of Wales.

Works carried out by A&P North East on the project included; fitting of a carousel to the main deck and under deck stiffening along with  fabrication and installation of a number of items including a forward cow catcher, bulwalk sections, A-Frame seats and plough carriage.

General Manager Ian Douglas commented, “The work scope was completed on time & on budget for Global Marine, We also carried out work assistance to erect & install the carousel.

The complete work package was initially layed out on a general arrangement with changes to the arrangement emerging as the project progressed with class approvals & client requirements.”
 

Categories: People & Company News Ship Repair & Conversion

Related Stories

First Green Methanol Bunkering of New Car Carrier Successfully Completed

RightShip Appoints Psaltaki Chief Product Officer

Svanehoj Appoints Larsen President

Current News

First Green Methanol Bunkering of New Car Carrier Successfully Completed

Egypt Looks to Sign Multi-Year LNG Supply Deal

Houthis Threaten Targeted Attacks on Shipping Companies Visiting Saudi Ports

DP World, EBRD Sign $28m Loan to Electrify Constanța Terminal Operations

Subscribe for Maritime Logistics Professional E‑News