Costa Concordia Salvage Update

Press Release
Tuesday, April 23, 2013

Salvors have successfully positioned the first port-side sponson that will be used in the 'parbuckling' stage of the wreck removal process.

Operations now continue with the installation of the second sponson, and eventually they will be welded on the hull of the wreck.

At the same time,  drillings for next 10 underwater holes will carry on in order to position remaining platforms 2 & 3.

In this major feat of salvage and underwater engineering altogether 438 workers based at Giglio are currently engaged in operations to float the wrecked cruise ship and tow it away.

Categories: Salvage Technology Underwater Engineering

Related Stories

Cavotec Inks Southern California Shore Power Order

How JobMarineMan Is Building a Direct Crew Recruitment Ecosystem

Ammonia-Fueled Vessel Delivered to EXMAR

Current News

BIMCO, ICS Report Warns of Possible Shortage of STCW Certified Officers

France to Export Four Barley Cargoes to China

Mitsubishi Shipbuilding Receives Order for Ammonia Fuel Handling System

Cavotec Inks Southern California Shore Power Order

Subscribe for Maritime Logistics Professional E‑News