Costa Concordia Salvage Update

Press Release
Tuesday, April 23, 2013

Salvors have successfully positioned the first port-side sponson that will be used in the 'parbuckling' stage of the wreck removal process.

Operations now continue with the installation of the second sponson, and eventually they will be welded on the hull of the wreck.

At the same time,  drillings for next 10 underwater holes will carry on in order to position remaining platforms 2 & 3.

In this major feat of salvage and underwater engineering altogether 438 workers based at Giglio are currently engaged in operations to float the wrecked cruise ship and tow it away.

Categories: Salvage Technology Underwater Engineering

Related Stories

PERC Leads Fuel Conversation at Port of the Future Conference

Exmar Deploys NexusWave Across Fleet

MacGregor Launches Balanced Lashing System

Current News

Argentina Grain Exports Rise From Strong Harvest

Tanker Bound for Cuba with Fuel Cargo Diverts to Trinidad

Independent Port Consultants Announces New Hires

US Crude Being Shipped to Asia Via Panama Canal

Subscribe for Maritime Logistics Professional E‑News