Costa Concordia Salvage Update

Press Release
Tuesday, April 23, 2013

Salvors have successfully positioned the first port-side sponson that will be used in the 'parbuckling' stage of the wreck removal process.

Operations now continue with the installation of the second sponson, and eventually they will be welded on the hull of the wreck.

At the same time,  drillings for next 10 underwater holes will carry on in order to position remaining platforms 2 & 3.

In this major feat of salvage and underwater engineering altogether 438 workers based at Giglio are currently engaged in operations to float the wrecked cruise ship and tow it away.

Categories: Salvage Technology Underwater Engineering

Related Stories

Greensea IQ Launches Autonomous Hull and Infrastructure Inspection Robot

ABB to Power Allseas’ Heavy Transport Vessel Grand Tour

SeaTac Marine Leverage MARAD Grant for New Equipment

Current News

Sheskharis Terminal Pauses Loadings Following Drone Attack

European Wheat Rises as Black Sea Disruptions Persist

AD Ports Group Reports Strong Q2

Drone Attack Sparks Fire at Ust-Luga Port

Subscribe for Maritime Logistics Professional E‑News