Costa Concordia Salvage Update

Press Release
Tuesday, April 23, 2013

Salvors have successfully positioned the first port-side sponson that will be used in the 'parbuckling' stage of the wreck removal process.

Operations now continue with the installation of the second sponson, and eventually they will be welded on the hull of the wreck.

At the same time,  drillings for next 10 underwater holes will carry on in order to position remaining platforms 2 & 3.

In this major feat of salvage and underwater engineering altogether 438 workers based at Giglio are currently engaged in operations to float the wrecked cruise ship and tow it away.

Categories: Salvage Technology Underwater Engineering

Related Stories

Great Circle Group Expands Marine Technology Services to Cape Cod

Terminal Portuario de Guayaquil Training Simulators Boost Efficiency, Safety

Wasaline Hits Carbon Neutrality Mark

Current News

Singapore Maritime Foundation Hosts MaritimeONE Scholarship Award Ceremony 2025

Great Circle Group Expands Marine Technology Services to Cape Cod

OPCSA Orders Eight Hybrid Konecranes RTG Cranes

Adani Group Refuses Sanctioned Vessels at its Ports

Subscribe for Maritime Logistics Professional E‑News