Aker Solutions, IHI Partnership on LNG Terminal

Tuesday, August 25, 2009

The Aker Solutions and IHI partnership has received a signed Notice of Substantial Completion for Sempra LNG's Cameron LNG liquefied natural gas (LNG) receipt terminal near Lake Charles, La.
 
The Cameron LNG terminal project combined Aker Solutions' expertise in regasification engineering, construction management, commissioning and start-up with IHI's design and manufacturing knowledge of LNG storage and processing systems.
 
Cameron LNG's first commissioning cargo arrived June 21. A subsequent delivery was made on June 30. The terminal is capable of processing 1.5 billion standard cubic feet per day (Bscf/d) of natural gas.
 
Aker Industrial Constructors was responsible for construction management of many subcontracts as well as self-performing portions of direct hire construction work.
 
Aker Bowen, a division of Aker Plant Services Group, was responsible for leading the joint team of Aker Solutions and IHI in commissioning and start-up.
 
Aker Solutions US, Inc. and IHI Inc. were the contracting parties responsible for delivering the project.

Categories: LNG

Related Stories

LNG Canada Produces First LNG for Export

Russian Yamal LNG Plant Ships First Cargo This Season Via Northern Sea Route

Port Arthur LNG Phase 2 Receives Non-FTA Export Authorization

Current News

Oil Supply to Outpace Demand in Medium-Term

Guinea Exports Record 48.6 Million Tons of Bauxite

ASRY Hosts First Innovation Forum with Lumofy

Osbit Opens New Offshore Wind Facility in Port of Blyth

Subscribe for Maritime Logistics Professional E‑News