Aker Solutions, IHI Partnership on LNG Terminal

Tuesday, August 25, 2009

The Aker Solutions and IHI partnership has received a signed Notice of Substantial Completion for Sempra LNG's Cameron LNG liquefied natural gas (LNG) receipt terminal near Lake Charles, La.
 
The Cameron LNG terminal project combined Aker Solutions' expertise in regasification engineering, construction management, commissioning and start-up with IHI's design and manufacturing knowledge of LNG storage and processing systems.
 
Cameron LNG's first commissioning cargo arrived June 21. A subsequent delivery was made on June 30. The terminal is capable of processing 1.5 billion standard cubic feet per day (Bscf/d) of natural gas.
 
Aker Industrial Constructors was responsible for construction management of many subcontracts as well as self-performing portions of direct hire construction work.
 
Aker Bowen, a division of Aker Plant Services Group, was responsible for leading the joint team of Aker Solutions and IHI in commissioning and start-up.
 
Aker Solutions US, Inc. and IHI Inc. were the contracting parties responsible for delivering the project.

Categories: LNG

Related Stories

Tallink Shuttle to Run Entirely on Renewable Energy

Green Hydrogen Project at Port of Klaipėda Enters Testing Phase

Panama President: Future Port Contracts Will Not Be Issued to a Single Operator

Current News

Victoria International Container Terminal Extends Contract to 2066

NYK Invests in Oceanic Constellations Tech Startup

Tallink Shuttle to Run Entirely on Renewable Energy

Green Hydrogen Project at Port of Klaipėda Enters Testing Phase

Subscribe for Maritime Logistics Professional E‑News