The Aker Solutions and IHI partnership has received a signed Notice of Substantial Completion for Sempra LNG's Cameron LNG liquefied natural gas (LNG) receipt terminal near Lake Charles, La.
 
The Cameron LNG terminal project combined Aker Solutions' expertise in regasification engineering, construction management, commissioning and start-up with IHI's design and manufacturing knowledge of LNG storage and processing systems.
 
Cameron LNG's first commissioning cargo arrived June 21. A subsequent delivery was made on June 30. The terminal is capable of processing 1.5 billion standard cubic feet per day (Bscf/d) of natural gas.
 
Aker Industrial Constructors was responsible for construction management of many subcontracts as well as self-performing portions of direct hire construction work.
 
Aker Bowen, a division of Aker Plant Services Group, was responsible for leading the joint team of Aker Solutions and IHI in commissioning and start-up.
 
Aker Solutions US, Inc. and IHI Inc. were the contracting parties responsible for delivering the project.

Categories: LNG

Related Stories

Court Rules on DP World Djibouti Case

As Energy Reliability Concerns Mount, Material Handling Professionals Urged to “Prepare with Propane”

Puerto Rico Inks LNG Contract with New Fortress Energy

Current News

Singapore Evaluates Ammonia Bunkering Solution

Europe’s Ports Call for Swift Adoption of IMO Net-Zero Framework

Hardik Gajjar Joins HDR as Maritime Planning Lead

Court Rules on DP World Djibouti Case

Subscribe for Maritime Logistics Professional E‑News