Aker Solutions, IHI Partnership on LNG Terminal

August 25, 2009

The Aker Solutions and IHI partnership has received a signed Notice of Substantial Completion for Sempra LNG's Cameron LNG liquefied natural gas (LNG) receipt terminal near Lake Charles, La.
 
The Cameron LNG terminal project combined Aker Solutions' expertise in regasification engineering, construction management, commissioning and start-up with IHI's design and manufacturing knowledge of LNG storage and processing systems.
 
Cameron LNG's first commissioning cargo arrived June 21. A subsequent delivery was made on June 30. The terminal is capable of processing 1.5 billion standard cubic feet per day (Bscf/d) of natural gas.
 
Aker Industrial Constructors was responsible for construction management of many subcontracts as well as self-performing portions of direct hire construction work.
 
Aker Bowen, a division of Aker Plant Services Group, was responsible for leading the joint team of Aker Solutions and IHI in commissioning and start-up.
 
Aker Solutions US, Inc. and IHI Inc. were the contracting parties responsible for delivering the project.

LNG

Logistics News

Inland Tank-Barge Safety Guide Updated

Inland Tank-Barge Safety Guide Updated

BY THE NUMBERS: Copper is Cargo Theft King

BY THE NUMBERS: Copper is Cargo Theft King

SeaTac Marine Leverage MARAD Grant for New Equipment

SeaTac Marine Leverage MARAD Grant for New Equipment

First Green Methanol Bunkering of New Car Carrier Successfully Completed

First Green Methanol Bunkering of New Car Carrier Successfully Completed

Subscribe for Maritime Logistics Professional E‑News

Sources say that the $30 billion Morocco-Germany power cable has been stalled due to governance differences.
The new British PM has promised to cap the cost of bus tickets
Cathay Pacific reports stronger first-half profits on travel and cargo demand